# Hotel Room Refurbishment Materials List and Floor-by-Floor Delivery Plan

> **Question:** How do you draw up a materials list for a hotel room refurbishment?
> **Short answer:** Draw up the list for one room first, then multiply it by the number of rooms.
> Source: https://aksco.com.tr/en/insights/hotel-room-refurbishment-materials-list/ · Last updated: 2026-10-23 · Publisher: AKSCO Ticaret ve Tedarik

For hotel owners, operators and their purchasing and technical teams: a per-room item list, the total quantity formula, a batch delivery plan, the mock-up room step, the quote layout and what changes when the hotel is outside Türkiye.

Published: 2026-10-23 · Last updated: 2026-10-23 · 16 min read · Prepared by AKSCO · [Editorial standards](https://aksco.com.tr/en/editorial-standards/)

Contents

1. Short answer
2. Per-room item list
3. Total quantity: per room × number of rooms + spares
4. Floor-by-floor and block-by-block batch delivery plan
5. Mock-up room: before the series order
6. New hotel: pre-opening purchase list
7. Supplying a hotel outside Türkiye
8. How the quote is laid out
9. Scope: materials, and installation within İstanbul

## How do you draw up a materials list for a hotel room refurbishment?

**Draw up the list for one room first, then multiply it by the number of rooms.** For each room type (standard, family, suite) write the items and the quantity per room; the order quantity is *quantity per room × number of rooms + spare allowance*, and the spare allowance is yours to set. Delivery is split into batches floor by floor or block by block, each defined by floor, room-number range and delivery date. Before the series order, a mock-up room confirms colour, light and hardware on site. On the quote, material lines and installation stay on separate lines; installation is arranged only for work within İstanbul, on request. For a hotel outside Türkiye the materials are delivered under the agreed Incoterms® 2020 rule to the named place. On standard items the quote is sent within 1 business day.

## Per-room item list

Every item that will change in the refurbishment is one line. Fill in the table for one room type: you decide which items change and how many of each the room has; we do not suggest quantities. The third column is what the line needs to say for the quote to be given for the right product; leave blank what you do not know — a photo or the label of the existing product works too.

Hotel room refurbishment — per-room item list

| Group | Item | Information to give for the quote | Unit | Quantity per room (you fill in) |
| --- | --- | --- | --- | --- |
| Paint & finishes | Wall paint (interior) | Type (e.g. emulsion, silicone-modified), finish (matt, silk matt), colour code (RAL or the manufacturer’s colour card), container size | litre | … |
| Paint & finishes | Ceiling paint | Type, colour, container size | litre | … |
| Paint & finishes | Primer | Type to suit the surface (plaster, old paint, damp areas) | litre | … |
| Paint & finishes | Filler and touch-up plaster | Type, pack size | kg | … |
| Paint & finishes | Paint or varnish for doors, frames and woodwork | Type (water-based, solvent-based), colour code | litre | … |
| Paint & finishes | Silicone and acrylic sealant | Where used (bathroom, frames), colour | cartridge | … |
| Lighting | Ceiling light or downlight | Mounting type, cut-out diameter, power (W), luminous flux (lm), colour temperature (K) | each | … |
| Lighting | Lamp (bulb) | Cap type (E27, E14, GU10…), power, colour temperature, dimmer compatibility | each | … |
| Lighting | Bedside wall light or table lamp | Size, lamp holder, switched or not, cable outlet | each | … |
| Lighting | Bathroom and mirror light | Size, IP rating, colour temperature | each | … |
| Bathroom | Toilet seat and cistern fittings | Model or dimensions of the existing toilet | set | … |
| Bathroom | Basin mixer tap | Type, connection size, finish colour | each | … |
| Bathroom | Shower set (hand shower, hose, holder or slide rail) | Hose length, connection, finish colour | set | … |
| Bathroom | Mirror | Size, illuminated or not, anti-fog or not | each | … |
| Bathroom | Bathroom accessories | Towel rail, toilet roll holder, hook, soap dish; series and finish colour | set | … |
| Textiles | Curtains (sheer, drape, blackout) | Window size | each | … |
| Textiles | Duvet cover set, sheets, pillowcases | Bed size | set | … |
| Textiles | Towels and bath mat | Type (hand, bath) | each | … |
| Furniture hardware | Hinges and drawer runners | Size and fixing type of the existing part | each | … |
| Furniture hardware | Handles and knobs | Hole spacing, finish colour | each | … |
| Furniture hardware | Clothes hangers | Type | each | … |
| Furniture hardware | Furniture felt pads and glides | Diameter, floor type | each | … |
| Electrical | Socket outlet (earthed, with USB) | Series name, colour, frame compatibility | each | … |
| Electrical | Switch (single, double, two-way) | Series name, colour | each | … |
| Electrical | TV and data outlet | Series name, connection type | each | … |
| Electrical | Frame (cover plate) | Series, number of gangs, horizontal or vertical | each | … |
| Door hardware | Door handle and rose | Door thickness, hand, finish colour; if tied to a lock system, the system’s make and model | set | … |
| Door hardware | Door closer | Door weight and width | each | … |
| Door hardware | Door stop and door viewer | Type, finish colour | each | … |
| Door hardware | Room number sign | Material, size, list of numbers | each | … |
| Consumables | Masking tape and protective sheeting | Width, roll length | roll | … |
| Consumables | Brushes, rollers and sandpaper | Type to suit the paint, grit number | each | … |
| Consumables | Wall plugs, screws and fixings | Size, wall type | pack | … |
| Consumables | Floor protection board or sheet | Size | roll | … |

The list is a starting frame: delete the lines your room does not have and add those it does. The quantity column is left blank on purpose; you fill it in for the room type and the scope of the refurbishment.

On paint and finish lines the quantity comes from square metres, not from a count: enter the room’s width, length and ceiling height (or the area to be painted), the paint type and the number of coats in the [paint quantity calculator](https://aksco.com.tr/en/tools/paint-quantity-calculator/) and take the litres per room from there. Give colour codes as a RAL code or the manufacturer’s colour card reference, not as a screenshot.

Bathroom lines are kept short here: give the model or dimensions of the existing toilet, the tap connection size and the finish colour; a photo of each fitting works too. If the hotel is outside Türkiye, see the electrical note under supplying a hotel outside Türkiye before filling in the electrical and lighting lines.

## Total quantity: per room × number of rooms + spares

Once the per-room list is final, the order quantity for each line comes from a single formula:

**Total = (quantity per room × number of rooms of that type) + spare allowance**  
If there is more than one room type, the subtotal is worked out for each type separately and added up on the line. You set the spare allowance.

For example, if you wrote 3 per room for an item and are refurbishing 40 rooms of that type, the subtotal is 3 × 40 = 120; you add the spare allowance on top of that number. This is an arithmetic example, not a suggested quantity per room.

When deciding on spares, look at these questions:

- **Can it be damaged during installation?** Glass, mirrors, ceramics and parts with delicate surfaces.
- **Will the same item be available later?** With socket-and-switch series, taps, luminaires and door handles, if the same series and colour cannot be found later, rooms end up different from one another.
- **Must it come from the same batch?** The same paint colour code can show a shade difference between production batches; buying the whole requirement in one go reduces this risk.
- **What is the pack unit?** The total is rounded up to whole cartons or tins; units per carton are stated on the quote.
- **How far away is the hotel?** For a hotel abroad, a missing item means another shipment; weigh that when you set spares for items that break easily or are hard to match later.

## Free per-room list and batch plan (Excel)

The 34 items of the table above are ready in 8 groups. Enter the number of rooms once, and the quantity per room and the spare allowance (%) on each line; the total is calculated as *quantity per room × number of rooms × (1 + spare allowance)*, rounded up. Mark each line Y (quote wanted) or N (not wanted). The second sheet holds the batch plan by floor, room-number range, delivery date and item group.

- [XLSX — Hotel Room Refurbishment Materials List (Excel, in English) — 3 sheets · 34 items / 8 groups · total quantity formula · floor / batch plan · no sign-up](https://aksco.com.tr/assets/docs/aksco-hotel-room-refurbishment-materials-list.xlsx)

The quantity, number-of-rooms and spare-allowance cells are blank: the file suggests no quantity or rate. If there is more than one room type, copy the sheet for each type. No prices or brands are embedded.

## Floor-by-floor and block-by-block batch delivery plan

If the hotel stays open during the refurbishment, rooms are taken out of sale floor by floor or block by block. If all the material arrives on day one, it takes up storage space; if it arrives late, a closed room sits empty. That is why there is one order and delivery comes batch by batch. Before asking for a quote, write this information in a table for each batch:

Information needed for each batch in the delivery plan

| Information | Why it is needed |
| --- | --- |
| Batch name or sequence | The batch breakdown on the quote and the delivery note match this name |
| Floor or block | Which floor or building the materials go to; handling is planned accordingly |
| Room-number range | Which rooms are in this batch; if room types are mixed, the number of rooms per type is written too |
| Batch quantity | Per-room list × number of rooms in this batch; also note which batch the spares come with |
| Delivery date | The day the rooms come out of sale; each item’s lead time is checked against it |
| Delivery point and access | Hotel address, service entrance, goods lift, delivery-time restrictions; whether carrying to the floors is included is stated on the quote. For a hotel abroad, the named place of the Incoterms® 2020 rule |
| Receiving contact | The person who signs the delivery note and counts the items, with phone number |

You can send the table as an Excel file; there is no need to change its row and column layout.

Because items come from different dealers, those with different lead times can arrive separately; each item’s lead time is on the quote, so an item that will not make its batch date shows up there and you can bring its order forward. For deliveries within Türkiye, because an invoice must be issued within 7 days of delivery (Tax Procedure Law art. 231/5), batches spread over a longer period are invoiced by batch group or invoiced for the whole order before delivery. At each delivery it is enough to check the items on the delivery note against the batch list.

Why a batch finishes with its slowest line, and what the number of sources does to on-time delivery, is explained in [how supplier count affects delivery time](https://aksco.com.tr/en/insights/supplier-count-and-delivery-time/).

[Send your room list and request a quote](https://aksco.com.tr/en/request-a-quote/)

## Mock-up room: before the series order

A method used in hotel refurbishment is to fit out one room completely with the new materials before moving on to all the others: the mock-up room. Two taps, two colour temperatures or two socket series that look the same on paper look different in the room; seeing the difference before the series order catches in one room a mistake that would otherwise spread across the whole order.

1. **Mock-up room list.** A one-room version of the per-room list is requested as a separate small order or as a separate line on the quote. For a hotel abroad, the mock-up order can travel as its own small shipment; ask for it to be quoted with its own delivery rule.
2. **Fit-out.** The room is prepared exactly as it will be in the series work.
3. **Approval.** Hotel management and, if there is one, the interior designer inspect the room in daylight and under evening lighting; items to change are noted.
4. **Finalising the list.** The changes go into the per-room list; models, colour codes and quantities are fixed from this room.
5. **Series order and batches.** The final list is multiplied by the number of rooms and split into the batch plan.

If approval takes a long time, check the quote’s validity period: if it has expired, the series order is re-priced under current conditions. Export quotes with a foreign-currency cost base may carry a shorter validity; the validity period and the exchange-rate basis are stated on the quote. If you want the series order to use exactly the model and colour code of the mock-up room, write it on the line; if you specify a brand, we follow it exactly.

## New hotel: pre-opening purchase list

For a new hotel the per-room list is drawn up the same way; the difference is that items which stay in place during a refurbishment also go on the list. Add these lines to the table above:

- Bed, base and headboard; wardrobe, bedside table, desk, chair, luggage rack
- Television and wall bracket, minibar, in-room safe
- Hair dryer, kettle and hospitality tray, glasses
- Pillows, duvet or blanket, mattress protector, bathrobe
- Waste bin, bathroom scale, in-room information material and signage

Guest-room consumables (amenities, toilet paper, cleaning chemicals) do not go on this list; their quantity is calculated separately from occupied room nights. Working back from the opening date, ask first about the long-lead items (furniture, made-to-measure curtains).

In hotel projects the terms FF&E (furniture, fixtures and equipment) and OS&E (operating supplies and equipment) are used for these purchases. Where the line between the two falls differs between projects and brand standards, so this list keeps item names rather than those categories.

## Supplying a hotel outside Türkiye

AKSCO is a corporate supplier based in İstanbul and does not hold stock of its own: we take your list, source the items and send a written quote line by line. For a hotel project outside Türkiye the list, the per-room method and the batch plan stay the same; the request needs these in addition:

- **Delivery rule.** An Incoterms® 2020 rule with a named place, e.g. “FCA İstanbul, Incoterms® 2020” or “DAP [hotel address], Incoterms® 2020”. The rule decides who pays carriage, who arranges any insurance, and where the risk passes; a rule without a named place leaves the main question open.
- **Batches as shipments.** If batches are to leave Türkiye separately, say so and give each batch’s name and room-number range, so that the shipments and their packing lists follow your floor plan. Any special packing or marking requirement, for example cartons marked by floor or room range, is stated in the request.
- **Electrical items.** Sockets, switches, plugs and lamps have to suit the destination’s plug and socket standard and supply voltage, and any approval or marking required there; write these on the electrical and lighting lines. A series sold in Türkiye does not necessarily fit another country’s sockets or wall boxes.
- **Documents and packaging.** Which of A.TR, EUR.1 or a certificate of origin your customs authority needs, and whether wood packaging is acceptable and must carry the ISPM 15 mark.
- **Currency and VAT.** The currency you want the quote in. A qualifying export delivery is exempt from Turkish VAT; whether an order qualifies depends on how it is shipped — see the questions in the [RFQ template](https://aksco.com.tr/en/insights/request-for-quotation-rfq-template/) guide.

We supply the materials. We do not act as a customs broker, freight operator or insurance agent; those are handled by the relevant party or partner under the agreed Incoterm, and the quote states which cost sits where. How the rules, documents and wood packaging work is explained in [export shipping from Türkiye](https://aksco.com.tr/en/insights/export-shipping-from-turkiye/).

## How the quote is laid out

For a refurbishment quote to be readable, materials and installation are not mixed on the same line. Our quote is laid out like this:

Line layout of a hotel refurbishment quote

| Line type | What the line says |
| --- | --- |
| Material lines | Line no., item, specification (model, colour code, size), unit, total quantity, unit price, amount. Prices exclude VAT; for deliveries in Türkiye one list can carry different VAT rates, and each item’s rate is shown on its own line |
| Batch breakdown (on request) | Annex table: how many of each item go in which batch, and the delivery date |
| Mock-up room (on request) | One room’s materials as a separate line or a separate quote |
| Installation line (İstanbul only, on request) | Separate item: which work (for example painting, or replacing luminaires, taps or sockets), its unit and quantity. Not buried in the material price |
| Delivery terms | Delivery point, lead time, and whether freight and carrying to the floors are included; for an export order, the Incoterms® 2020 rule and named place |

If you want the lines in your own list’s numbering, we keep that order.

If you specify brands we follow them exactly; otherwise we present original and equivalent options side by side — with an original / equivalent alternative column if you wish. When an equivalent makes sense is covered in [“or equivalent” in procurement](https://aksco.com.tr/en/insights/original-or-equivalent-procurement/).

When you request a quote, send the following; if not everything is ready, start with what you have and we will get in touch to complete the rest together:

- Room types and the number of rooms of each type
- The completed per-room list (Excel or a photo of the table)
- Photos, labels or model details of the existing products; colour codes
- Batch plan: floor or block, room-number range, delivery date
- Delivery address and access restrictions
- For a hotel abroad: destination country and city, the Incoterms® 2020 rule and named place you prefer, the documents you need and the quote currency
- If the hotel is in İstanbul: whether you want installation, and for which work

**Quote time:** within 1 business day on standard items. On standard items we aim to quote the same business day. Custom production, imports or 50+ line lists can take longer; when they do, we tell you the timeline in writing on the day we receive the request.

## Scope: materials, and installation within İstanbul

**Scope:** For the work covered on this page, we supply **materials**. We do not provide interior design, permits and approvals, or the management of the refurbishment works. Within İstanbul, installation crews for work such as painting and replacing luminaires, taps and sockets can be arranged on request and shown as a separate line in the quote. Beyond that — across all 81 provinces of Türkiye and on export shipments abroad — our commitment ends with delivery of the materials to the delivery point named on the quote, under the Incoterm agreed for export orders.

We have no price list; price, availability and lead time are checked for each request and stated on the quote.

## Frequently Asked Questions

How do I prepare a materials list for a hotel room refurbishment? 

Start with a list for one room type: in the paint and finishes, lighting, bathroom, textiles, furniture hardware, electrical, door hardware and consumables groups, write every item that will change and its quantity per room. Then multiply each line by the number of rooms of that type and add the spare allowance. If there is more than one room type, make a separate list for each.

How much spare stock should I order? 

You decide; we do not suggest a fixed rate. Decide by looking at items that can be damaged during installation (glass, mirrors, ceramics), items whose series may not be available later (socket-and-switch series, taps, luminaires) and paint that must come from the same production batch.

Do you also provide installers? 

For work within İstanbul, installation crews for work such as painting and replacing luminaires, taps and sockets can be arranged on request as a separate item and shown on a separate line of the quote. Elsewhere in Türkiye and on export orders we supply materials only; our commitment ends with delivery of the materials to the delivery point named on the quote.

Can you deliver floor by floor? 

One order, delivered batch by batch. For each batch write the floor or block, the room-number range, the delivery date and the receiving contact. Each item’s lead time is on the quote; an item that will not make its batch date shows up there, and you can bring its order forward.

Can you supply a hotel outside Türkiye? 

Yes, as an export shipment. Name the destination, the Incoterms 2020 rule with a named place, the documents your customs authority needs and the quote currency; on an export quote the delivery point and the split of responsibility are stated under the agreed rule. Customs clearance, freight and insurance sit with the party the rule assigns them to.

Why build a mock-up room? 

A tap, a light colour or a socket series that looks the same on paper can look different in the room. Fitting out one room with the new materials and approving it before the series order catches the mistake in one room; models, colour codes and quantities are fixed from that room.

Can this list be used for a new hotel? 

Yes, with the same method. Items that stay in place during a refurbishment (bed, base, main furniture, television, minibar, in-room safe, hair dryer and the like) are added to the list. Guest-room consumables are calculated separately from occupied room nights.

## Related guides

### Paint Quantity Calculator

From square metres to litres, coats and tin sizes: paint needed per room.

[Read more](https://aksco.com.tr/en/tools/paint-quantity-calculator/)

### Export Shipping from Türkiye

Incoterms, document sets and ISPM 15 wood packaging.

[Read more](https://aksco.com.tr/en/insights/export-shipping-from-turkiye/)

### Request for Quotation (RFQ) Template

The five fields that make quotes comparable, plus currency and delivery rule when goods cross a border.

[Read more](https://aksco.com.tr/en/insights/request-for-quotation-rfq-template/)

### How Supplier Count Affects Delivery Time

A batch finishes with its slowest line.

[Read more](https://aksco.com.tr/en/insights/supplier-count-and-delivery-time/)

### Electrical & Lighting

Luminaires, lamps, sockets and switches.

[Read more](https://aksco.com.tr/en/products/electrical-lighting/)

### Paint & Building Materials

Interior paint, primers, plaster and construction chemicals.

[Read more](https://aksco.com.tr/en/products/paint-building-materials/)

## Send your list — your quote is ready within 1 business day.

A list, a photo or an Excel file — whatever is easiest. On standard items we aim to quote the same business day. Custom production, imports or 50+ line lists can take longer; when they do, we tell you the timeline in writing on the day we receive the request.

[Request a Quote](https://aksco.com.tr/en/request-a-quote/)[ Send an Email](mailto:info@aksco.com.tr?subject=Quote%20request%20%E2%80%94%20AKSCO&body=Hello%2C%0D%0A%0D%0APlease%20quote%20for%20the%20list%20below%20%28or%20attached%29.%0D%0A%0D%0ACompany%3A%0D%0ADelivery%20city%20and%20country%3A%0D%0AWhen%20needed%3A%0D%0AItems%20%28product%20%E2%80%93%20quantity%20%E2%80%93%20brand/model%20if%20any%29%3A%0D%0A%0D%0A)[Message on WhatsApp](https://wa.me/905343356922?text=Hello%2C%20I%20would%20like%20a%20quote.%0ACompany%3A%0AItems%3A%0ADelivery%20city%3A)

---

AKSCO Ticaret ve Tedarik — https://aksco.com.tr