Hotel Room Refurbishment Materials List and Floor-by-Floor Delivery Plan

For hotel owners, operators and their purchasing and technical teams: a per-room item list, the total quantity formula, a batch delivery plan, the mock-up room step, the quote layout and what changes when the hotel is outside Türkiye.

Short answer

How do you draw up a materials list for a hotel room refurbishment?

Draw up the list for one room first, then multiply it by the number of rooms. For each room type (standard, family, suite) write the items and the quantity per room; the order quantity is quantity per room × number of rooms + spare allowance, and the spare allowance is yours to set. Delivery is split into batches floor by floor or block by block, each defined by floor, room-number range and delivery date. Before the series order, a mock-up room confirms colour, light and hardware on site. On the quote, material lines and installation stay on separate lines; installation is arranged only for work within İstanbul, on request. For a hotel outside Türkiye the materials are delivered under the agreed Incoterms® 2020 rule to the named place. On standard items the quote is sent within 1 business day.

Per-room item list

Every item that will change in the refurbishment is one line. Fill in the table for one room type: you decide which items change and how many of each the room has; we do not suggest quantities. The third column is what the line needs to say for the quote to be given for the right product; leave blank what you do not know — a photo or the label of the existing product works too.

Hotel room refurbishment — per-room item list
GroupItemInformation to give for the quoteUnitQuantity per room (you fill in)
Paint & finishesWall paint (interior)Type (e.g. emulsion, silicone-modified), finish (matt, silk matt), colour code (RAL or the manufacturer’s colour card), container sizelitre…
Paint & finishesCeiling paintType, colour, container sizelitre…
Paint & finishesPrimerType to suit the surface (plaster, old paint, damp areas)litre…
Paint & finishesFiller and touch-up plasterType, pack sizekg…
Paint & finishesPaint or varnish for doors, frames and woodworkType (water-based, solvent-based), colour codelitre…
Paint & finishesSilicone and acrylic sealantWhere used (bathroom, frames), colourcartridge…
LightingCeiling light or downlightMounting type, cut-out diameter, power (W), luminous flux (lm), colour temperature (K)each…
LightingLamp (bulb)Cap type (E27, E14, GU10…), power, colour temperature, dimmer compatibilityeach…
LightingBedside wall light or table lampSize, lamp holder, switched or not, cable outleteach…
LightingBathroom and mirror lightSize, IP rating, colour temperatureeach…
BathroomToilet seat and cistern fittingsModel or dimensions of the existing toiletset…
BathroomBasin mixer tapType, connection size, finish coloureach…
BathroomShower set (hand shower, hose, holder or slide rail)Hose length, connection, finish colourset…
BathroomMirrorSize, illuminated or not, anti-fog or noteach…
BathroomBathroom accessoriesTowel rail, toilet roll holder, hook, soap dish; series and finish colourset…
TextilesCurtains (sheer, drape, blackout)Window sizeeach…
TextilesDuvet cover set, sheets, pillowcasesBed sizeset…
TextilesTowels and bath matType (hand, bath)each…
Furniture hardwareHinges and drawer runnersSize and fixing type of the existing parteach…
Furniture hardwareHandles and knobsHole spacing, finish coloureach…
Furniture hardwareClothes hangersTypeeach…
Furniture hardwareFurniture felt pads and glidesDiameter, floor typeeach…
ElectricalSocket outlet (earthed, with USB)Series name, colour, frame compatibilityeach…
ElectricalSwitch (single, double, two-way)Series name, coloureach…
ElectricalTV and data outletSeries name, connection typeeach…
ElectricalFrame (cover plate)Series, number of gangs, horizontal or verticaleach…
Door hardwareDoor handle and roseDoor thickness, hand, finish colour; if tied to a lock system, the system’s make and modelset…
Door hardwareDoor closerDoor weight and widtheach…
Door hardwareDoor stop and door viewerType, finish coloureach…
Door hardwareRoom number signMaterial, size, list of numberseach…
ConsumablesMasking tape and protective sheetingWidth, roll lengthroll…
ConsumablesBrushes, rollers and sandpaperType to suit the paint, grit numbereach…
ConsumablesWall plugs, screws and fixingsSize, wall typepack…
ConsumablesFloor protection board or sheetSizeroll…

The list is a starting frame: delete the lines your room does not have and add those it does. The quantity column is left blank on purpose; you fill it in for the room type and the scope of the refurbishment.

On paint and finish lines the quantity comes from square metres, not from a count: enter the room’s width, length and ceiling height (or the area to be painted), the paint type and the number of coats in the paint quantity calculator and take the litres per room from there. Give colour codes as a RAL code or the manufacturer’s colour card reference, not as a screenshot.

Bathroom lines are kept short here: give the model or dimensions of the existing toilet, the tap connection size and the finish colour; a photo of each fitting works too. If the hotel is outside Türkiye, see the electrical note under supplying a hotel outside Türkiye before filling in the electrical and lighting lines.

Total quantity: per room × number of rooms + spares

Once the per-room list is final, the order quantity for each line comes from a single formula:

Total = (quantity per room × number of rooms of that type) + spare allowance
If there is more than one room type, the subtotal is worked out for each type separately and added up on the line. You set the spare allowance.

For example, if you wrote 3 per room for an item and are refurbishing 40 rooms of that type, the subtotal is 3 × 40 = 120; you add the spare allowance on top of that number. This is an arithmetic example, not a suggested quantity per room.

When deciding on spares, look at these questions:

  • Can it be damaged during installation? Glass, mirrors, ceramics and parts with delicate surfaces.
  • Will the same item be available later? With socket-and-switch series, taps, luminaires and door handles, if the same series and colour cannot be found later, rooms end up different from one another.
  • Must it come from the same batch? The same paint colour code can show a shade difference between production batches; buying the whole requirement in one go reduces this risk.
  • What is the pack unit? The total is rounded up to whole cartons or tins; units per carton are stated on the quote.
  • How far away is the hotel? For a hotel abroad, a missing item means another shipment; weigh that when you set spares for items that break easily or are hard to match later.

Free per-room list and batch plan (Excel)

The 34 items of the table above are ready in 8 groups. Enter the number of rooms once, and the quantity per room and the spare allowance (%) on each line; the total is calculated as quantity per room × number of rooms × (1 + spare allowance), rounded up. Mark each line Y (quote wanted) or N (not wanted). The second sheet holds the batch plan by floor, room-number range, delivery date and item group.

The quantity, number-of-rooms and spare-allowance cells are blank: the file suggests no quantity or rate. If there is more than one room type, copy the sheet for each type. No prices or brands are embedded.

Floor-by-floor and block-by-block batch delivery plan

If the hotel stays open during the refurbishment, rooms are taken out of sale floor by floor or block by block. If all the material arrives on day one, it takes up storage space; if it arrives late, a closed room sits empty. That is why there is one order and delivery comes batch by batch. Before asking for a quote, write this information in a table for each batch:

Information needed for each batch in the delivery plan
InformationWhy it is needed
Batch name or sequenceThe batch breakdown on the quote and the delivery note match this name
Floor or blockWhich floor or building the materials go to; handling is planned accordingly
Room-number rangeWhich rooms are in this batch; if room types are mixed, the number of rooms per type is written too
Batch quantityPer-room list × number of rooms in this batch; also note which batch the spares come with
Delivery dateThe day the rooms come out of sale; each item’s lead time is checked against it
Delivery point and accessHotel address, service entrance, goods lift, delivery-time restrictions; whether carrying to the floors is included is stated on the quote. For a hotel abroad, the named place of the Incoterms® 2020 rule
Receiving contactThe person who signs the delivery note and counts the items, with phone number

You can send the table as an Excel file; there is no need to change its row and column layout.

Because items come from different dealers, those with different lead times can arrive separately; each item’s lead time is on the quote, so an item that will not make its batch date shows up there and you can bring its order forward. For deliveries within Türkiye, because an invoice must be issued within 7 days of delivery (Tax Procedure Law art. 231/5), batches spread over a longer period are invoiced by batch group or invoiced for the whole order before delivery. At each delivery it is enough to check the items on the delivery note against the batch list.

Why a batch finishes with its slowest line, and what the number of sources does to on-time delivery, is explained in how supplier count affects delivery time.

Send your room list and request a quote

Mock-up room: before the series order

A method used in hotel refurbishment is to fit out one room completely with the new materials before moving on to all the others: the mock-up room. Two taps, two colour temperatures or two socket series that look the same on paper look different in the room; seeing the difference before the series order catches in one room a mistake that would otherwise spread across the whole order.

  1. Mock-up room list. A one-room version of the per-room list is requested as a separate small order or as a separate line on the quote. For a hotel abroad, the mock-up order can travel as its own small shipment; ask for it to be quoted with its own delivery rule.
  2. Fit-out. The room is prepared exactly as it will be in the series work.
  3. Approval. Hotel management and, if there is one, the interior designer inspect the room in daylight and under evening lighting; items to change are noted.
  4. Finalising the list. The changes go into the per-room list; models, colour codes and quantities are fixed from this room.
  5. Series order and batches. The final list is multiplied by the number of rooms and split into the batch plan.

If approval takes a long time, check the quote’s validity period: if it has expired, the series order is re-priced under current conditions. Export quotes with a foreign-currency cost base may carry a shorter validity; the validity period and the exchange-rate basis are stated on the quote. If you want the series order to use exactly the model and colour code of the mock-up room, write it on the line; if you specify a brand, we follow it exactly.

New hotel: pre-opening purchase list

For a new hotel the per-room list is drawn up the same way; the difference is that items which stay in place during a refurbishment also go on the list. Add these lines to the table above:

  • Bed, base and headboard; wardrobe, bedside table, desk, chair, luggage rack
  • Television and wall bracket, minibar, in-room safe
  • Hair dryer, kettle and hospitality tray, glasses
  • Pillows, duvet or blanket, mattress protector, bathrobe
  • Waste bin, bathroom scale, in-room information material and signage

Guest-room consumables (amenities, toilet paper, cleaning chemicals) do not go on this list; their quantity is calculated separately from occupied room nights. Working back from the opening date, ask first about the long-lead items (furniture, made-to-measure curtains).

In hotel projects the terms FF&E (furniture, fixtures and equipment) and OS&E (operating supplies and equipment) are used for these purchases. Where the line between the two falls differs between projects and brand standards, so this list keeps item names rather than those categories.

Supplying a hotel outside Türkiye

AKSCO is a corporate supplier based in İstanbul and does not hold stock of its own: we take your list, source the items and send a written quote line by line. For a hotel project outside Türkiye the list, the per-room method and the batch plan stay the same; the request needs these in addition:

  • Delivery rule. An Incoterms® 2020 rule with a named place, e.g. “FCA İstanbul, Incoterms® 2020” or “DAP [hotel address], Incoterms® 2020”. The rule decides who pays carriage, who arranges any insurance, and where the risk passes; a rule without a named place leaves the main question open.
  • Batches as shipments. If batches are to leave Türkiye separately, say so and give each batch’s name and room-number range, so that the shipments and their packing lists follow your floor plan. Any special packing or marking requirement, for example cartons marked by floor or room range, is stated in the request.
  • Electrical items. Sockets, switches, plugs and lamps have to suit the destination’s plug and socket standard and supply voltage, and any approval or marking required there; write these on the electrical and lighting lines. A series sold in Türkiye does not necessarily fit another country’s sockets or wall boxes.
  • Documents and packaging. Which of A.TR, EUR.1 or a certificate of origin your customs authority needs, and whether wood packaging is acceptable and must carry the ISPM 15 mark.
  • Currency and VAT. The currency you want the quote in. A qualifying export delivery is exempt from Turkish VAT; whether an order qualifies depends on how it is shipped — see the questions in the RFQ template guide.

We supply the materials. We do not act as a customs broker, freight operator or insurance agent; those are handled by the relevant party or partner under the agreed Incoterm, and the quote states which cost sits where. How the rules, documents and wood packaging work is explained in export shipping from Türkiye.

How the quote is laid out

For a refurbishment quote to be readable, materials and installation are not mixed on the same line. Our quote is laid out like this:

Line layout of a hotel refurbishment quote
Line typeWhat the line says
Material linesLine no., item, specification (model, colour code, size), unit, total quantity, unit price, amount. Prices exclude VAT; for deliveries in Türkiye one list can carry different VAT rates, and each item’s rate is shown on its own line
Batch breakdown (on request)Annex table: how many of each item go in which batch, and the delivery date
Mock-up room (on request)One room’s materials as a separate line or a separate quote
Installation line (İstanbul only, on request)Separate item: which work (for example painting, or replacing luminaires, taps or sockets), its unit and quantity. Not buried in the material price
Delivery termsDelivery point, lead time, and whether freight and carrying to the floors are included; for an export order, the Incoterms® 2020 rule and named place

If you want the lines in your own list’s numbering, we keep that order.

If you specify brands we follow them exactly; otherwise we present original and equivalent options side by side — with an original / equivalent alternative column if you wish. When an equivalent makes sense is covered in “or equivalent” in procurement.

When you request a quote, send the following; if not everything is ready, start with what you have and we will get in touch to complete the rest together:

  • Room types and the number of rooms of each type
  • The completed per-room list (Excel or a photo of the table)
  • Photos, labels or model details of the existing products; colour codes
  • Batch plan: floor or block, room-number range, delivery date
  • Delivery address and access restrictions
  • For a hotel abroad: destination country and city, the Incoterms® 2020 rule and named place you prefer, the documents you need and the quote currency
  • If the hotel is in İstanbul: whether you want installation, and for which work

Quote time: within 1 business day on standard items. On standard items we aim to quote the same business day. Custom production, imports or 50+ line lists can take longer; when they do, we tell you the timeline in writing on the day we receive the request.

Scope: materials, and installation within İstanbul

Scope: For the work covered on this page, we supply materials. We do not provide interior design, permits and approvals, or the management of the refurbishment works. Within İstanbul, installation crews for work such as painting and replacing luminaires, taps and sockets can be arranged on request and shown as a separate line in the quote. Beyond that — across all 81 provinces of Türkiye and on export shipments abroad — our commitment ends with delivery of the materials to the delivery point named on the quote, under the Incoterm agreed for export orders.

We have no price list; price, availability and lead time are checked for each request and stated on the quote.

Frequently Asked Questions

How do I prepare a materials list for a hotel room refurbishment?

Start with a list for one room type: in the paint and finishes, lighting, bathroom, textiles, furniture hardware, electrical, door hardware and consumables groups, write every item that will change and its quantity per room. Then multiply each line by the number of rooms of that type and add the spare allowance. If there is more than one room type, make a separate list for each.

How much spare stock should I order?

You decide; we do not suggest a fixed rate. Decide by looking at items that can be damaged during installation (glass, mirrors, ceramics), items whose series may not be available later (socket-and-switch series, taps, luminaires) and paint that must come from the same production batch.

Do you also provide installers?

For work within İstanbul, installation crews for work such as painting and replacing luminaires, taps and sockets can be arranged on request as a separate item and shown on a separate line of the quote. Elsewhere in Türkiye and on export orders we supply materials only; our commitment ends with delivery of the materials to the delivery point named on the quote.

Can you deliver floor by floor?

One order, delivered batch by batch. For each batch write the floor or block, the room-number range, the delivery date and the receiving contact. Each item’s lead time is on the quote; an item that will not make its batch date shows up there, and you can bring its order forward.

Can you supply a hotel outside Türkiye?

Yes, as an export shipment. Name the destination, the Incoterms 2020 rule with a named place, the documents your customs authority needs and the quote currency; on an export quote the delivery point and the split of responsibility are stated under the agreed rule. Customs clearance, freight and insurance sit with the party the rule assigns them to.

Why build a mock-up room?

A tap, a light colour or a socket series that looks the same on paper can look different in the room. Fitting out one room with the new materials and approving it before the series order catches the mistake in one room; models, colour codes and quantities are fixed from that room.

Can this list be used for a new hotel?

Yes, with the same method. Items that stay in place during a refurbishment (bed, base, main furniture, television, minibar, in-room safe, hair dryer and the like) are added to the list. Guest-room consumables are calculated separately from occupied room nights.

Send your list — your quote is ready within 1 business day.

A list, a photo or an Excel file — whatever is easiest. On standard items we aim to quote the same business day. Custom production, imports or 50+ line lists can take longer; when they do, we tell you the timeline in writing on the day we receive the request.