Monday – Friday, 09:00 – 18:00 (UTC+3) WhatsApp 24/7

Generator and UPS Sizing Calculator

Continuous kVA, the peak demand when the largest motor starts, the candidate generator rating, and a UPS runtime that accounts for the rate effect and ageing.

Calculator

From a load list to the continuous power, the peak demand when the largest motor starts and a candidate generator rating; on the UPS side, the realistic runtime of a battery string.

Luminaires, sockets, small appliances

Server room, network cabinet, video recorder

Air conditioning and ventilation; compressor starting is counted separately below

The assumption that not everything runs at once. 1 = everything together

The calculator assumes the set rating is at 0.8 lagging; confirm in the manufacturer’s datasheet

Headroom for load added later

The largest motor that starts on its own; enter 0 if there is none. For a motor on a variable frequency drive, enter the drive’s nameplate rating

Printed on the nameplate or data sheet: the starting-current ratio (IA/IN) on IEC motors; a NEMA motor’s nameplate carries a locked-rotor kVA/HP code letter instead — read what the letter means in kVA/HP from the motor manufacturer’s data sheet. The calculation takes running apparent power as ≈ HP × 1, so the two read as approximately (≈) the same number. 6.5 is only an EXAMPLE — while the field holds it the results carry “(example value)”

The starting method can double or halve the generator size required. A VFD has no starting inrush; in exchange the set is OVERSIZED for the harmonic load it presents

A set that only runs when the mains fails is an ESP. This choice only names the rating type in the results; you type the permitted average load in the next field

The 24-hour average load, in percent, that the rating type you chose permits. Read it from the generator manufacturer’s data sheet (ISO 8528 rating type, e.g. ESP/PRP/COP) or from your own copy of ISO 8528-1. 68 is only an EXAMPLE — while the field holds it the results carry “(example value)”

Only the part that genuinely needs uninterrupted supply — not the whole building

Number of batteries in series × 12 V (for example 20 × 12 V = 240 V)

The nameplate rating — may be quoted at the 20-hour (C20) rate; use the rate in the datasheet

How far you allow the battery to be discharged

Conversion efficiency from battery DC to the AC load

A lead-acid battery’s nameplate Ah may be quoted at the 20-hour (C20) rate; use the rate in the datasheet. Over a 10-minute UPS discharge it delivers roughly half that, and IEEE 485 additionally recommends a 1.25 factor for end of life. Together that is about a 55–65% allowance. Lithium nameplates are quoted at 1C and do not need an allowance this large

Result

—Continuous load (with diversity)
—Apparent power required
—Peak demand at starting (skVA)
—Lower size — for the continuous load
—Upper size — to start the motor within an acceptable voltage dip
—What governs the size
—Average load — at the lower / upper size
—Load factor assessment
—UPS runtime
—Ah needed for 10 minutes

The calculation runs entirely in your browser; nothing you type is sent to our servers. Only if you press “Request a quote with this calculation” are your inputs and the result written to your browser’s session storage, so it can be carried into the quote form.

Worked example

Opened with its default case — Lighting and socket load (kW): 15 · IT and server load (kW): 8 · HVAC load (kW): 20 — the calculator returns the figures below. They are written out here so the output is readable without running JavaScript: in print, with scripts disabled, or by a search engine.

Worked example — inputs
InputValue
Lighting and socket load (kW)15
IT and server load (kW)8
HVAC load (kW)20
Other continuous load (kW)0
Diversity factor0.8
Power factor (cos φ)0.8
Allowance for future load (%)20
Shaft power of the largest motor (kW)11
Starting-current ratio IA/IN or kVA/HP (from the motor nameplate)6.5
Motor starting methodDirect on line (DOL) — the heaviest start
Generator rating type (ISO 8528-1)ESP — emergency standby
Average load limit % (from your standard or the manufacturer’s data sheet)68
Load to be supported by the UPS (kW)5
Battery string voltage (V)240
Battery capacity (Ah)9
Depth of discharge (%)80
UPS efficiency (%)90
Ageing and high-rate allowance (%)60
Worked example — results
ResultValue
Continuous load (with diversity)53.1 kW (80% diversity, +20% margin, motor included)
Apparent power required66.3 kVA (cos φ 0.8)
Peak demand at starting (skVA)147.4 kVA · 11 kW motor, direct on line (DOL), starting ratio 6.5 kVA/HP (example value)
Lower size — for the continuous load100 kVA (ESP) (calculated: 97.6 kVA) (example value)
Upper size — to start the motor within an acceptable voltage dipSame as the lower size — starting is not the governing case
What governs the sizeContinuous load · ESP (emergency standby)
Average load — at the lower / upper size66% (100 kVA) · 66% (100 kVA)
Load factor assessmentWithin limits — inside the 68% average load limit for ESP (example value)
UPS runtime7.5 minutes (622 Wh usable)
Ah needed for 10 minutes12.1 Ah · 240 V string

Change any field above and the calculator recomputes; this table is the default case only. Thresholds and class values that come from a standard are not built into the tool: you type the values you read from your own standard or specification into the relevant fields. The pre-filled thresholds in this table are only an example — read yours from your own standard.

Short answer

How do you size a standby generator?

Two limits are calculated and the larger one wins. The first is the continuous load: sum the loads, apply a diversity factor, add a future allowance, divide by the power factor to get kVA (or by 0.8 if the load’s power factor is higher, since set ratings assume 0.8 lagging), then divide again by the rating type’s permitted average load, which you read from your own copy of ISO 8528-1 or from the manufacturer’s data sheet. The second is the starting demand of the largest motor, which for a direct-on-line start is roughly kW ÷ 0.746 × the starting ratio (kVA/HP, or IA/IN) on the motor nameplate, against a running load of about kW ÷ 0.746 kVA. Where starting decides the machine, a soft starter or star-delta may cost less than the next generator size up — price both. The tool reports both limits, says which one governs, and warns when the resulting set would run below 30% average load — the wet stacking zone that damages a diesel engine over time.

The two limits

How each limit is built
LimitBuilt fromWhat it protects
Continuous(Σ kW × diversity × (1 + future allowance)) ÷ cos φ — or ÷ 0.8 if that is larger, since set ratings assume 0.8 lagging — plus the largest motor’s running kVA, then ÷ the permitted average load for the rating typeThe engine and alternator running within their duty rating
StartingMotor kW ÷ 0.746 × the nameplate starting ratio (kVA/HP) × the starting-method factor, divided by an accepted inrush multiple — 3× as our screening assumption; the real limit is the alternator’s starting-kVA curveThe voltage dip when the motor starts (Cummins T-030 treats 35% as acceptable unless the project specifies otherwise), and everything that trips because of it

Both are reported. When starting is the governing case the tool says so explicitly, because that is the situation where changing the starter — not the generator — may be the cheaper fix; price both.

The diversity factor is the input people get wrong in the safe direction, which is still wrong. Entering 1 assumes every load runs simultaneously and produces a set that will spend its life lightly loaded. A measured figure from a maximum-demand recording — or, failing that, a considered planning assumption (we use 0.7–0.85 for a mixed building) — gives a better machine.

Starting method changes everything

Starting method against inrush
MethodRelative starting currentTrade-off
Direct on line (DOL)Full locked-rotor currentCheapest starter, largest generator; hardest on the driven machine
Star-deltaAbout one thirdCheap, but there is a transition transient and reduced starting torque
Soft starterAbout 45%, adjustableSmooth ramp; still draws more than running current
Variable frequency driveNo inrush at allThe set is instead oversized for harmonic load — Cummins T-030: about 40% for PWM drives, about 2× for current-source drives, sized on the drive’s nameplate, not the motor’s

The last row is the one that surprises people: a VFD removes the starting problem and introduces a different one. The generator is sized to carry the harmonic distortion the drive presents, which is why the calculator treats a VFD as a continuous oversizing requirement rather than as a peak. It applies a factor of 1.6 — our planning assumption between the two T-030 figures; once the drive type is known, confirm with 1.4 or 2.

The starting ratio on the motor nameplate or data sheet is a very useful number in this calculation and an easy one to overlook: locked-rotor kVA per horsepower on NEMA motors (given there as a code letter), the IA/IN ratio on IEC motors. The calculator takes it as an input and carries no table of code-letter bands — read it from the nameplate. Two motors of the same rating can differ markedly in inrush.

ESP, PRP, COP — what the rating means

ISO 8528-1 rating types
RatingPermitted useHours per yearAverage load and overload
ESP — emergency standbyMains failure onlyLimited (set by the standard)Defined in the standard — read the values from your own copy
PRP — primeVariable loadNo hour limitAverage load defined in the standard; any overload margin is in the manufacturer’s data sheet, not in the standard
COP — continuousConstant loadNo hour limitDefined in the standard — read the values from your own copy

The hour limits and the permitted average-load percentages are not printed here: read them from your own copy of ISO 8528-1 or from the manufacturer’s data sheet and type the percentage into the “Average load limit %” field. The same physical machine carries different kVA figures under each rating, which is why comparing two quotes without checking the rating type compares nothing. A set quoted at its standby rating and one quoted at its prime rating are not the same size.

Too big is a fault, not a safety margin

The instinct to round generously upward causes a specific and expensive failure. A diesel engine running below roughly 30% of its rating does not reach its designed cylinder temperature; unburnt fuel and lubricating oil accumulate in the exhaust and turbo — wet stacking. The symptoms are visible smoke, oil at the exhaust and progressive loss of output, and the remedy is either a load bank exercise programme or a correctly sized machine.

This is why the calculator reports the average load factor at both candidate sizes and warns below 30%. When starting demand forces a large machine that will then idle, check whether changing the starting method is the better answer before accepting a set that will be under-loaded for twenty years.

Sizing the UPS battery honestly

A UPS battery does not deliver its nameplate capacity in a UPS discharge, and this alone can put a runtime calculation out by a factor of two. Three corrections belong in every estimate:

  1. The rate effect. A lead-acid nameplate Ah may be quoted at the 20-hour (C20) rate; use the rate in the datasheet. Over the ten minutes a UPS actually runs, the same battery delivers roughly half that energy.
  2. End-of-life ageing. IEEE 485 recommends a 1.25 factor, because a battery at the end of its service life is expected to retain 80% of its rated capacity and the system must still work then.
  3. Depth of discharge. Taking a VRLA battery to 100% discharge shortens its life sharply. The calculator caps the input at 90% and says so in the result rather than accepting a figure that would destroy the battery.

Together the first two are why the ageing allowance defaults to 60%. Lithium batteries are a different case: their nameplates are quoted at 1C, so the rate correction is far smaller and an allowance this large would understate the runtime.

What to send us for a quote

Send the calculator output with the motor nameplate details, the fuel tank autonomy you need in hours and whether the set will sit indoors, in a canopy or on a roof. Those three decide the exhaust, the acoustic specification and the fuel arrangement, which can be a large share of the installed cost. We quote the set, the transfer arrangement, batteries and the consumables — filters, oil, coolant, fuel treatment — on one list, and the maintenance parts are the same ones you will reorder for years.

Frequently Asked Questions

What size generator do I need for a given load?

It depends on the load mix, the rating and the largest motor. Work two limits and take the larger. Continuous: the loads times diversity times the future allowance, divided by the power factor (or by 0.8 if the load’s power factor is higher, since set ratings assume 0.8 lagging), plus the running kVA of the largest motor, then divided by the average-load limit you read from your own standard or data sheet. Starting: the motor’s starting kVA (kW ÷ 0.746 × the nameplate starting ratio × the starting-method factor) divided by the multiple of its rating the set can accept, for which the calculator uses 3× as a screening assumption. The calculator shows both, says which one sets the size and rounds up to the next standard size; the values pre-filled in the two threshold fields are examples only.

Why is starting current so much larger than running current?

A motor at standstill looks like a short circuit to the supply until it builds back-EMF. The locked-rotor current is a multiple of the running current, and the ratio on the nameplate or data sheet tells you which. That inrush lasts seconds but the generator has to carry it without the voltage collapsing.

Is a bigger generator always safer?

No. Below about 30% average load a diesel engine wet stacks: unburnt fuel and oil collect in the exhaust and turbocharger, producing smoke and progressive loss of output. An oversized set is a maintenance liability, not a margin.

What is the difference between ESP, PRP and COP ratings?

They are duty ratings under ISO 8528-1. ESP is emergency standby with limited annual hours; PRP is prime, unlimited hours at a variable load; COP is continuous at a constant load. The same machine carries a different kVA figure under each, so two quotes are only comparable when the rating is the same.

Why does my UPS run for less time than the battery Ah suggests?

Because the nameplate Ah may be quoted at a slow rate such as 20 hours (C20); use the rate in the datasheet. Over the ten minutes a UPS actually delivers, a lead-acid battery gives roughly half that energy, and IEEE 485 recommends a further 1.25 end-of-life factor. Together those account for much of the gap between Ah and runtime.

Can you supply the generator consumables as well?

Yes — filters, oil, coolant, fuel treatment, batteries and the spares you will reorder on a schedule, on one account. Send the set model and the service interval and we will build the parts list against it.

Send your list — your quote is ready within 1 business day.

A list, a photo or an Excel file — whatever is easiest. On standard items we aim to quote the same business day. Custom production, imports or 50+ line lists can take longer; when they do, we tell you the timeline in writing on the day we receive the request.